Kentucky Street Project in Sturgeon Bay

Sturgeon Bay City Engineer Tony Depies has issued a timetable for paving Kentucky Street downtown Sturgeon Bay. Depies says the plan is to put the first layer of asphalt in the north end of the nearby alley as soon as possible next week. He notes that it could be as late as Wednesday depending on weather & its affect on other projects. Depies also says the week of September 24th, the contractor will return to finish sewer & storm sewer work & then all paving will be completed the first week in October, except for the portion of the alley closest to Louisiana Street. Completion of the project will be dependent on repairs to a building damaged during the 4th Avenue rehabilitation project.